Completion of a New Building at the Chino Plant
DISCO Corporation (Headquarters: Ota-ku, Tokyo; President: Kazuma Sekiya) has announced that the construction of a new building was completed on Thursday, June 10, 2010 at its Chino Plant in Nagano Prefecture.
 |
At Chino Plant, DAIICHI COMPONENTS, LTD., DISCO's wholly owned subsidiary, manufactures products.
|
Objectives of the New Building Construction
|
<Improvement of BCM* Readiness>
|
 |
-
|
Since the new building adopts an earthquake-absorbing structure, even when a large earthquake hits this area, damage to the plant can be minimized, so as to realize an environment where products can be supplied in a stable manner at the time of a disaster.
|
 |
* BCM: Business Continuity Management |
 |
|
<Improvement of Efficiency by Consolidating Manufacturing Locations>
|
 |
-
|
Work efficiency will be improved by consolidating the functions that are currently dispersed in obsolete manufacturing facilities.
|
 |
|
→
|
Most of the production lines of the existing buildings will be transferred to the new building.
|
Operation Start
 |
The operation will start in stages.
|
Supplemental Information
|

|
Official name of the plant
|
:
|
DISCO Chino Plant
|
|

|
Total floor area
|
:
|
About 19,800 m2 (six stories above ground)
|
|

|
Total amount invested
|
:
|
About three billion yen
|
|

|
Construction start
|
:
|
July 2008
|
|

|
Total site area of the Chino Plant
|
:
|
Approximately 70,416 m2
|
|

|
Use of the new building
|
:
|
Manufacturing of existing DAIICHI COMPONENTS products and some DISCO products
|
|
 |




|